Home Business ECG Faces 36 Percent Payment Shortfall for Gas in 2023, Report Finds

ECG Faces 36 Percent Payment Shortfall for Gas in 2023, Report Finds

0
Electricity Company Of Ghana
Electricity Company Of Ghana

A report by the Public Interest Accountability Committee(PIAC) reveals a 36 percent shortfall in the Electricity Company of Ghana’s payments in accordance with the cash waterfall mechanism (CWM) for gas in 2023.

In the 2023 edition of the report, PIAC disclosed that ECG paid an approximate amount of GHS 250 million as against an expected payment of GHS 385 million.

The report showed that the outstanding debts to be paid by ECG for gas used for the year 2023 were GHS 140 million.

The Cash Waterfall Mechanism (CWM) and Natural Gas Clearinghouse (NGCH) set out the principles, methodology, and processes for determining and disbursing tariff revenue collected by the Electricity Company of Ghana (ECG) to various beneficiaries along the electricity value chain.

Accordingly, Ghana National Gas Company Limited (GNGLC),  Ghana National Petroleum Company (GNPC), and other stakeholders in the value chain are paid directly by CWM as a percentage of the invoice amount submitted for each month.

The report said that although allocations were made in the months of July and August, ECG did not make payments for those allocations.

The report said PIAC observed that GNGLC’s indebtedness to GNPC continued to rise despite the use of the Cash Waterfall Mechanism to address the legacy debts.

The report noted that this trend, if not mitigated, could impair the operational viability of GNGLC.

Send your news stories to newsghana101@gmail.com Follow News Ghana on Google News

NO COMMENTS

LEAVE A REPLY

Please enter your comment!
Please enter your name here

error: Content is protected !!
WP Radio
WP Radio
OFFLINE LIVE
Exit mobile version