Tema Port Expansion
Seven Shortlisted For Tema Port Expansion

Marine works at the ongoing Tema Port expansion project being undertaken by the China Harbour Engineering Company Limited (CHEC) is on schedule with over 53 per cent work complete.

The marine work which forms one of the three components of the expansion project, consist of the construction of a breakwater, quay walls, deep water berths, and access channels for mega vessels.

Mr Frank Ebo Brown, Legal, License and Permits Manager, Meridian Port Services Limited (MPS), the company carrying out the expansion revealed this to the Ghana News Agency in an interview.

Mr Brown said with the current pace of work, the first two berths of 700 metres of quay wall, under the expansion project, would be ready for use by the end of June 2019.

He added that the third and fourth berths would be ready in 2020 and 2022 respectively when the one billion US Dollar project would be completed.

The expansion work is supposed to reclaim a total of 120 hectares of land from the sea, and to provide deeper berths which would make it easy for mega vessels that require about 15 to 16 metre draft to berth.

He explained that when the first two berths become operational in 2019, it would increase vessel operations at the port as currently the deepest berth at the Tema Port was 11.5 metres.

According to him, commencement of other works which include a building to accommodate all public authorities operating at the Port, a workshop and an MPS office building was underway.

He explained that the expanded area would also have a 40 megawatt power station to serve as a backup for the national grid which would ensure the efficiency of the operations of the facility.

Mr Brown disclosed that since the Port was a security zone, it would also have a gate complex which would use an optical character recognition system, license plate recognition system and scanners to ensure that only recognized vehicles and persons entered the facility.

Mr Emmanuel Ohene Addo, Operational Manager at MPS, on his part stated that seven new Ship to Shore Cranes, post panama, and 20 new Rubber Tie Ganty Cranes (RTGS) would be received in Ghana towards the opening of the first two berths.

Mr Addo added that two mobile harbour cranes would also be used at the new berths adding that they would be used to compliment the ship to shore cranes.

He explained that whereas the ship to shore cranes were large and used electricity, the mobile harbour cranes operates on diesel and smaller in size making it convenient to be used at the shallow areas of the berths.

Disclaimer: News Ghana is not responsible for the reportage or opinions of contributors published on the website.

Send your news stories to [email protected] and via WhatsApp on +1-508-812-0505 

Previous articleAGI business indicator shows a downward shift in business confidence
Next articleStarting 1st June GHS will Begin using IPV
The Ghana news Agency (GNA) was established on March 5, 1957, i.e. on the eve of Ghana's independence and charged with the "dissemination of truthful unbiased news". It was the first news agency to be established in Sub-Saharan Africa. GNA was part of a comprehensive communication policy that sought to harness the information arm of the state to build a viable, united and cohesive nation-state. GNA has therefore been operating in the unique role of mobilizing the citizens for nation building, economic and social development, national unity and integration.

LEAVE A REPLY

Please enter your comment!
Please enter your name here