The fiscal terms include royalty of 7.5% for oil since the water depth is in excess of 400 mters; gas royalty of 5%, corporate tax of 35%. GNPC has a carried interest of 15%; and additional paid interest of 5%. The working interest of the partners therefore amount to ENI Ghana (44%), Vitol Ghana (35%) and GNPC (20%).
In spite of these gains the company is likely to make from the deal, the Government has further over-exposed the country to too many risks due the decision to buy all the gas produced by the contractor. The exposure takes the form of guarantees and security to keep gas price at US$9.8 per mmBtu and to support the Gas Sales Agreement.
This is where the real challenge is. The over-generous concessions the Government and GNPC are providing to the Contractors are examined here.
The Government and GNPC have offered through the Supplementary Agreement to make the initial gas price of US$9.8/mmBtu viable by providing a fiscal package to the tune of US$250 million. A total of US$125 million will be provided by GNPC upfront, whilst the remaining fiscal concessions amounting to another US$125 million to be provided by Government will ran over the project life.
As per the Supplementary Agreement, for the contractors to execute the second phase project (Gas), GNPC is required to make upfront payments of US$125 million to ensure that the contractor makes an NPV of US$125 million based on the initial oil price of US$90 per bbl and gas price of US$9.8 per mmBtu.
The contractors must make an NPV of US$125m at all times. Therefore, if the initial price changes such that the contractors will not make an NPV of US$125 million at any point in time, GNPC is required within 3 months of any shortfall occurring, to implement alternative mechanism to eliminate the shortfall; or pay cash to the contractors if the mechanisms have not been implemented.
Per the deal, GNPC has two options for executing its upfront payments to the Contractors: Cash contribution of the total amount of $125 million, or the Contractor over-lift of oil due GNPC to the tune of $105 million plus GNPC cash purchase of remaining oil barrels in stock to the tune of $20 million at the beginning of production.
The implication of this is that, there is no room for the contractors to make a loss at any time or for their profit levels to decrease; and the state is obliged to assume the full risk of a loss occurring to the contractors through GNPC paying cash to offset any decrease in the contractors’ profitability.
In addition, the Government must issue a Sovereign Guarantee of $125 million to pay for the shortfall in case GNPC defaults.
The assumption of these risks by the state alone is too high in an industry that is very volatile. Since, the Contractors already make substantial profits from the oil project, the risk of a loss to the contractors must be shared with the state rather than the state entirely assuming the risks.
Although, the guarantees in the deal are required to make a Gas Sales Agreement effective; whilst guarantees are normal with international transactions such as this, some of the guarantees provided in the term sheet for the security package are disturbing. At most, they undermine Ghana’s sovereignty by tying down the hand of the Minister of Finance, GNPC and violating sections of the Petroleum Revenue Management Act 2011 (Act 815).
Further, GNPC shall not sell gas in any currency apart from US Dollars conflicting with the domestic currency regulations.
These disturbing guarantees are examined: The Escrow Disbursement Account; Escrow Reserve Holding Account; and Payment of GNPC’s Net Carried and Participating Interest into the main Escrow Disbursement Account.
According to the term sheet, GNPC is required to open a US Dollar main Escrow Disbursement Account, which shall receive revenues from the following sources: Domestic gas sales revenue including GNPC’s net carried and participating interest from Sankofa-Gye Nyame, Jubilee and TEN gas revenues.
In addition, all funds representing GNPC’s share from the Petroleum Holding Fund (excluding GNPCs cash calls and financing costs associated with petroleum agreements which are included in equity financing costs under section 7.2a of PRMA) and all revenues arising under gas sales agreements including on-sale gas by GNPC from existing and new developments from or across OCTP, Jubilee and TEN.
At this juncture, it is not clear why gas sales revenues from Jubilee and TEN projects must be transferred to the Escrow Account provided for in the Security Term Sheet for the OCTP Block; and managed by GNPC and the OCTP partners.
That is, the OCTP Contractors are invariably dictating the conditions under which Jubilee and TEN gas purchases will be paid for by GNPC. In the event that the Jubilee and TEN operators have different terms covering payment for their gas sales, the OCTP Gas Sales Agreement will be adversely affected. This also means that the Security package must not exclude Jubilee and TEN partners from the negotiations.
Also, the payment for gas sales from the Escrow Disbursement Account will be further backstopped by a World Bank Partial Risk Guarantee equivalent to $600 million and GNPC?s risk of default payment cover of $150 million by the International Development Authority (IDA). Notwithstanding these guarantees, the Government must issue a Sovereign Guarantee to cover any payment shortfalls after the Partial Risk Guarantee provided by the World Bank is exhausted.
Apart from the guarantees provided by the World Bank and IDA; and the Sovereign Guarantees provided by the Government for any shortfalls in payment for gas by GNPC, the corporation is further required to open a US Dollar Escrow Reserve Holding Account for the exclusive benefit of ENI Ghana and Vitol Ghana.
The Reserve Account shall be funded by GNPC before first gas with an amount equivalent to 4.5 months of the Contractors share of Annual Contract quantity. This requirement is more stringent given that Jubilee and TEN Gas sales payments Escrows require an amount equivalent to 3 months of annual contract quantity.
Source: Adnan Adams Mohammed