Barra Olympic Park – the biggest event cluster – is 92% ready, up from 89% last month, according to Rio2016.com.

The least advance is the velodrome, where work has reached 70%.
Two venues at Deodoro Park – the mountain bike and BMX courses – are already finished. Meanwhile Whitewater Stadium is 98% complete and Youth Arena 68% finished. Deodoro is the second-largest venue complex.
Work on the Olympic and Paralympic village is 97% complete while the golf course is 98% ready. Enditem
Source: Xinhua